Update 1 December 2017
This week we have continued to lay our new pipeline along Bramley Road moving towards the junction with Aldermaston Road. By this weekend there will be 20 metres of pipeline still to lay.
Next week we will be carrying out pressure tests on the pipe laid so far.
Once this work is complete we will need to lay the final 20 metres of pipe and connect the new water main to our existing water network in Aldermaston Road. For the safety of the public and our workforce, traffic lights will be in place along Aldermaston Road for the duration of this work. We expect the traffic lights to be in place between 11 and 15 December but we will keep you updated.
Campaign and Media Officer
Communications