Good afternoon,
Please see below an update on South East Water’s project to lay a new pipeline along Bramley Road, Little London.
Kind regards
Jess
Update 24 November 2017
Our work along Bramley Road is progressing well and we have laid 630 metres of our new pipeline with 480 metres of pipe still to install.
We are using a directional drilling technique which has allowed us to install the pipeline quicker than the traditional open cut method. We hope to continue using this method for the remainder of the pipeline but due to the complex ground materials we may need to install sections of the pipe via open cut techniques.
Thank you to local residents and motorists for your ongoing patience. We will keep you updated on our progress.
Jessica Gooch
Campaign and Media Officer
Communications
[+ go back...] |